Excel does not have a Gantt chart among the built-in chart types, but you can easily create one from a stacked bar chart. The picture below shows our initial data for building a Gantt chart.
Here’s what you need to do to create a Gantt chart:
- On the Advanced tab Insert (Insert) click Insert bar chart (Bar) and select subtype Ruled Stacked (Stacked Bar).
- Right-click on an empty construction area and in the context menu click Select data (Select Data).
- Press Add (Add) and add two rows of data: “Start Date” and “Duration».
- In the Horizontal axis labels (categories) (Horizontal (Category) Axis Labels) click Change (Edit) and select the range A4: A11.
- Press OK.
- Click on the legend on the right side of the chart and press the key Delete.
- The stages of the project (Foundation, Walls, and so on) are in reverse order. To fix this, right-click on the task names in the diagram, in the context menu, click Axis Format (Format Axis) and check the box Reverse order of categories (Categories in reverse order).
- Press Close (Close).
- Right-click on any red rectangle of the chart, in the context menu select Data series format (Format Data Series) > Fill (Fill) > No fill (No fill).
- Press Close (Close).
- Dates and times in Excel are stored as numbers, starting from January 1, 1900. Those. date June 1, 2012 corresponds to the date 41061, and July 13, 2012 – the number 41103.Right click on the dates on the chart, in the context menu click Axis Format (Format Axis) and set the values:
- Minimum (Minimum) equal 41061;
- Maximum (Maximum) equal to: 41103 + the duration of the last task, i.e. 41103 + 2 = 41105;
- for parameter Major divisions (Major units) enter a value 7.
- Press Close (Close).
Result: Gantt chart built in Excel.
Please note that tasksPlumbing” and “Electric» can be performed at the same time.